Project: BuckRV-8   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Buck Wyndham   -  
Project:   Vans - RV-8   -   VIEW REPORTS
Total Hours:3948.15
Start/Last Date:Jan 08, 2002 - No Finish Date
Engine:AeroSport Power IO-375-M1S
Propeller:Whirlwind 330-3B/72H-73 3-blade CS
Panel:G3X, G5, GTN650, GTR20, GTX45R, GMA245, GMC507
 
Friendly URL: https://eaabuilderslog.org?s=BuckRV-8

Home or Last Project Picture

May 05, 2007     Floorboard nutplates and gear towers - (2.0 hours)       Category: Fuselage
I installed about 30 more nutplates in the floor supports. All the ones in the "interior" of the floor are now done, and I got a good start on the ones along the edges. The edges are a lot harder to do, because of the lack of access, but I found that my pneumatic squeezer works pretty well there. I also had a chance to finally use that odd-shaped bucking bar I've had for so long now (Photo 1).

I also drilled out all the screw holes in the gear tower covers to #19 in preparation for installing nutplates.

It seems like I used half of my entire tool inventory installing the nutplates (Photo 2).


 